Waste water treatment plant for the Wilhelmshaven power plant

In the first half of 2009 HAGER + ELSÄSSER were awarded the contract for the realization of the waste water treatment plant for the new, ultra-modern coal fired 800 MW power plant “Wilhelmshaven”.

3D model of the waste water treatment plant

The waste water treatment consists of the following stages:

  • Chemical precipitation of sulphate and separation of suspended solids (first precipitation stage)
  • Chemical precipitation of heavy metals and sedimentation (second precipitation stage)
  • Waste water filtration
  • Sludge dewatering with fully automated chamber filter press


Having chosen this concept, our customer benefits from the following advantages:


  • Effluent values will be considerably lower than the legal discharge limits which will facilitate the approval procedures
  • The possibility to run each of the precipitation stages separately results in a high availability of the plant.
  • Compact design leads to considerable savings in the service building.
  • 2 tanks for deionised water are included in the scope of supply. 


Assembly of the water treatment plant will start in March 2010, commissioning is planned for the third quarter 2010.